MDE e-Permits

Reference Number: 13CH0023

Notice for Stormwater Associated with Construction Activity

Notice of Intent information is shown below. Click 'Show' for each section to view.

This Notice will be available for public viewing until 05/26/13

Erosion and Sediment Control » Show » Hide

Erosion and Sediment Control Plan Approval Authority: Baltimore City

Plan ID Number: ESCP-239475

State/Federal project without an SF number? No

General Information » Show » Hide

Permit Type: General


Responsible Person (Permittee)

Title: CEO

Name: Mr. Noah Rogers

Organization: FF Construction, Inc.


Address: 4 Wheel Drive, Annapolis, MD 20401

Mailing Address: P.O. Box 125, Annapolis, MD 20401


Contact Person

Title: Chief Construction Engineer

Name: Mr. Felix Fixit

Site Information » Show » Hide

Site/Project Name: Tower Ash

Phase: 2

Location Description: [Description]

Address: Baltimore, Baltimore City, MD 21202

Site Coordinates: 39.2833° N, 76.6167° W

Total Site Area: 187 acres

Total Disturbed Area: 35 acres


Site Contact Person

Title: Chief Construction Engineer

Name: Mr. Felix Fixit

Project Information » Show » Hide

Construction Project

Description: [Description]

Permit for Stormwater: 07PG1234

NPDES Number: 23450098

Type of Discharge: [Discharge Type]

Project Type: Private

Project Use: Commercial

SIC Number: 00052365


Discharge Information

Site Runoff: A municipal separate storm sewer system

Watershed Basin Code: [Code]

Are the receiving waters listed on the current Maryland 303(d) list as impaired? No

Cause of the impairment: Total Suspended Solids, Sedimentation/Siltation

Date comparing the eventual receiving waters with the Maryland 303(d) list: 03/25/2013


Impervious Surface and Runoff Curves

Runoff Curve: [Number]

Pre-Development: [Number]

Post Development: [Number]

Impervious Surface Area: 34 acres


Permanent Stormwater Management Facilities

Stormwater management facilities waived or exampted? No

Facility to be implemented: 2 infiltration trenches, 20 acres total drainage area

Facility to be implemented: 3 retention ponds, 4 acres total drainage area

Facility to be implemented: 1 wetland/shallow marsh, 10 acres total drainage area

Documents Uploaded » Show » Hide

Certificate of Compliance: wcc_certCompliance.jpg

Vicinity Map: baltimore_map.pdf